Brazos Bend Storage SLF
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
243 MW storage in Milam, Texas · In queue since September 2025 · Proposed COD September 2029
243 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntrySep 11, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-17
Project Details
State
Texas
County
Milam
Region
ERCOT
Developer
Grenergy USA
Utility
—
Entity
ERCOT
Point of Interconnection
345 kV Line (3765) GRISTMILL_5 to (39950) TNTNP_ONE_3
Data Source
Live · ERCOT
No news available for this project.