Wolf Bone North Energy Center
BetaActiveGas - Combined-CycleERCOTLive · ERCOT
1,204 MW generation in Reeves, Texas · In queue since October 2025 · Proposed COD November 2029
1,204 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 1m
Pre-Study0%
Queue EntryOct 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-11-01
Project Details
State
Texas
County
Reeves
Region
ERCOT
Developer
NRG Wolf Bone Energy Center LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 1 Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 2
Data Source
Live · ERCOT
No news available for this project.