Cazadores Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
301.62 MW generation in Duval, Texas · In queue since July 2025 · Proposed COD April 2029
301.62 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryJul 7, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-10
Project Details
State
Texas
County
Duval
Region
ERCOT
Developer
OCI Energy LLC
Utility
—
Entity
ERCOT
Point of Interconnection
(80079) CRUCE7A – (5901) MIGUEL5
Data Source
Live · ERCOT
No news available for this project.