Juanita Creek BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
303.6 MW storage in Matagorda, Texas · In queue since June 2025 · Proposed COD October 2031
303.6 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
6y 4m
Pre-Study0%
Queue EntryJun 19, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-10-01
Project Details
State
Texas
County
Matagorda
Region
ERCOT
Developer
Juanita Creek Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap CKT #39 between El Maton (#43990) and W.A.Parish (#44000)
Data Source
Live · ERCOT
No news available for this project.