Selenite Springs Solar
300 MW generation in Pecos, TX · In queue since April 2025 · Proposed COD August 2028
300 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
8 months
IA → COD
2y 8m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-08-30
State
TX
County
Pecos
Region
ERCOT
Developer
Selenite Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station