Caesar Storage
205.5 MW storage in Borden, Texas · In queue since July 2025 · Proposed COD November 2029
205.5 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-26
State
Texas
County
Borden
Region
ERCOT
Developer
Caesar Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
59916 Buck Canyon 345 kV
Data Source
Live · ERCOT
Solar project updates: EDP Renewables, Engie, Exus Renewables and more
Solar project milestones and portfolio finance updates for projects small and large on both sides of the meter across the United States.
Solar project updates: EDP Renewables, Engie, Exus Renewables and more
Solar project milestones and portfolio finance updates for projects small and large on both sides of the meter across the United States.
Solar project updates: EDP Renewables, Engie, Exus Renewables and more
Solar project milestones and portfolio finance updates for projects small and large on both sides of the meter across the United States.
Solar project updates: EDP Renewables, Engie, Exus Renewables and more
Solar project milestones and portfolio finance updates for projects small and large on both sides of the meter across the United States.
Last updated 2026-03-26