MilamStation Power Secured Gas Generation
BetaActiveGas - Combined-CycleERCOTLive · ERCOT
846 MW generation in Milam, Texas · In queue since March 2025 · Proposed COD November 2027
846 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 8m
Pre-Study0%
Queue EntryMar 24, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-01
Project Details
State
Texas
County
Milam
Region
ERCOT
Developer
Power Secured Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
#3377 LITTLE POND SWITCH 345kv
Data Source
Live · ERCOT
No news available for this project.