Bendito Wind
300 MW generation in Webb, Texas · In queue since July 2025 · Proposed COD July 2029
300 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-13
State
Texas
County
Webb
Region
ERCOT
Developer
Bendito Wind Farm, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV80220 Cenizo - 80079 Cruce Ckt 2
Data Source
Live · ERCOT
This billion-dollar company just built a $216M wind farm in South Texas
Renewable energy company, Terra-Gen, co-owned in part by a UAE company, celebrates $216 million Monte Cristo Windpower wind farm in...
This billion-dollar company just built a $216M wind farm in South Texas
Renewable energy company, Terra-Gen, co-owned in part by a UAE company, celebrates $216 million Monte Cristo Windpower wind farm in...
This billion-dollar company just built a $216M wind farm in South Texas
Renewable energy company, Terra-Gen, co-owned in part by a UAE company, celebrates $216 million Monte Cristo Windpower wind farm in...
This billion-dollar company just built a $216M wind farm in South Texas
Renewable energy company, Terra-Gen, co-owned in part by a UAE company, celebrates $216 million Monte Cristo Windpower wind farm in...
Last updated 2026-03-26