7L Solar SLF
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
71.6 MW generation in Dimmit, Texas · In queue since September 2025 · Proposed COD November 2029
71.6 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntrySep 22, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-11-13
Project Details
State
Texas
County
Dimmit
Region
ERCOT
Developer
7L Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 69kV 5870 Brundage - 5868 Big Wells
Data Source
Live · ERCOT
No news available for this project.