Meitner 2 Wind — Project Summary

Queue ID
ERCOT-29INR0103
Capacity
709.1 MW
Technology
Wind
Status
active
Location
Gray, Texas
Region
ERCOT
Developer
IP Meitner, LLC
IA Status

Meitner 2 Wind

BetaActiveWind - Wind TurbineERCOTLive · ERCOT

709.1 MW generation in Gray, Texas · In queue since June 2025 · Proposed COD June 2028

709.1 MW

Capacity

0

Components

9 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3 years

Pre-Study0%
Queue EntryJun 5, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

Texas

County

Gray

Region

ERCOT

Developer

IP Meitner, LLC

Utility

Entity

ERCOT

Point of Interconnection

79000 Gray Substation 345kV

Data Source

Live · ERCOT