Meitner 2 Wind
709.1 MW generation in Gray, Texas · In queue since June 2025 · Proposed COD June 2028
709.1 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
State
Texas
County
Gray
Region
ERCOT
Developer
IP Meitner, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
79000 Gray Substation 345kV
Data Source
Live · ERCOT
Intersect Power Tax Abatement Negotiations Pushed to September
The Gray County commissioners and Judge Porter held their first meeting for the month of August, starting with public comments regarding the...
Intersect Power Tax Abatement Negotiations Pushed to September
The Gray County commissioners and Judge Porter held their first meeting for the month of August, starting with public comments regarding the...
Intersect Power Tax Abatement Negotiations Pushed to September
The Gray County commissioners and Judge Porter held their first meeting for the month of August, starting with public comments regarding the...
Intersect Power Tax Abatement Negotiations Pushed to September
The Gray County commissioners and Judge Porter held their first meeting for the month of August, starting with public comments regarding the...
Last updated 2026-03-26