Firefly Fields Solar — Project Summary

Queue ID
ERCOT-29INR0085
Capacity
100.52 MW
Technology
Solar
Status
active
Location
Colorado, Texas
Region
ERCOT
Developer
Firefly Fields Energy Center LLC
IA Status

Firefly Fields Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

100.52 MW generation in Colorado, Texas · In queue since January 2025 · Proposed COD September 2028

100.52 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntryJan 13, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

Texas

County

Colorado

Region

ERCOT

Developer

Firefly Fields Energy Center LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV <57640> <Rock Island> - <7258> <Glidden>

Data Source

Live · ERCOT