Denver City - Mustang - Gas
BetaActiveGasERCOTLBNL
504 MW generation in Yoakum, TX · In queue since December 2024 · Proposed COD May 2029
504 MW
Capacity
1
Components
Gas
1y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryDec 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-31
Project Details
State
TX
County
Yoakum
Region
ERCOT
Developer
Golden Spread Electric Cooperative, Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
23876 CLEARFRK_5 345kV
Data Source
LBNL
No news available for this project.