Denver City - Mustang - Gas — Project Summary

Queue ID
ERCOT-29INR0083
Capacity
504 MW
Technology
Gas
Status
active
Location
Yoakum, TX
Region
ERCOT
Developer
Golden Spread Electric Cooperative, Inc.
IA Status
Facility Study

Denver City - Mustang - Gas

BetaActiveGasERCOTLBNL

504 MW generation in Yoakum, TX · In queue since December 2024 · Proposed COD May 2029

504 MW

Capacity

1

Components

Gas

1y 3m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 5m

Facilities Study50%
Queue EntryDec 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-31

Project Details

State

TX

County

Yoakum

Region

ERCOT

Developer

Golden Spread Electric Cooperative, Inc.

Utility

Entity

ERCOT

Point of Interconnection

23876 CLEARFRK_5 345kV

Data Source

LBNL