Amphion Solar
BetaActiveSolarERCOTLBNL + Live
507.57 MW generation in Atascosa, TX · In queue since October 2024 · Proposed COD September 2028
507.57 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryOct 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
TX
County
Atascosa
Region
ERCOT
Developer
Blue Heron Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
TAP 345KV (#5709) FLOWERTON - (#5901) SAN MIGUEL LINE Ckt FOWRTN_SMIGL2
Data Source
LBNL + Live
No news available for this project.