Rippling Curve Peaking Power
BetaActiveGasERCOTLBNL
208 MW generation in Harris, TX · In queue since September 2024 · Proposed COD January 2029
208 MW
Capacity
1
Components
Gas
1y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 4m
Facilities Study50%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-01
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
OxyVinyls LP
Utility
—
Entity
ERCOT
Point of Interconnection
41580 TIDAL__X06B8 138kV
Data Source
LBNL
No news available for this project.