Veco Ranch Solar SLF — Project Summary

Queue ID
ERCOT-29INR0045
Capacity
152.5 MW
Technology
Solar
Status
active
Location
Webb, TX
Region
ERCOT
Developer
Orion US Land Holding Co LLC
IA Status
Facility Study

Veco Ranch Solar SLF

BetaActiveSolarERCOTLBNL

152.5 MW generation in Webb, TX · In queue since July 2024 · Proposed COD August 2029

152.5 MW

Capacity

1

Components

Solar

1y 8m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 1m

Facilities Study50%
Queue EntryJul 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-08-30

Project Details

State

TX

County

Webb

Region

ERCOT

Developer

Orion US Land Holding Co LLC

Utility

Entity

ERCOT

Point of Interconnection

8283 ASHERTON4A 138kV

Data Source

LBNL

No news available for this project.