Homestead Power
BetaActiveGasERCOTLBNL + Live
260.3 MW generation in Austin, TX · In queue since July 2024 · Proposed COD December 2029
260.3 MW
Capacity
1
Components
Gas
1y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 5m
Facilities Study50%
Queue EntryJul 30, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-15
Project Details
State
TX
County
Austin
Region
ERCOT
Developer
Homestead Power LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138 kV New Bremen #7271
Data Source
LBNL + Live