Cavell Wind
BetaActiveWindERCOTLBNL + Live
658.8 MW generation in Castro, TX · In queue since July 2024 · Proposed COD July 2029
658.8 MW
Capacity
1
Components
Wind
1y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntryJul 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-30
Project Details
State
TX
County
Castro
Region
ERCOT
Developer
IP Cavell, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1
Data Source
LBNL + Live