Commodus 2 Wind
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
641.48 MW generation in Swisher, Texas · In queue since March 2025 · Proposed COD July 2029
641.48 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntryMar 3, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-30
Project Details
State
Texas
County
Swisher
Region
ERCOT
Developer
IP Blackwell II, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900)