Skeeter Solar
BetaActiveSolarERCOTLBNL + Live
251 MW generation in Jones, TX · In queue since June 2024 · Proposed COD December 2028
251 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryJun 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-02
Project Details
State
TX
County
Jones
Region
ERCOT
Developer
Mesquite Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
345 kV SWEETWATER EAST (11420) - LONG CREEK (1435)
Data Source
LBNL + Live
No news available for this project.