Buzios BESS SLF
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
— storage in Motley, Texas · In queue since April 2025 · Proposed COD July 2029
—
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 3m
Pre-Study0%
Queue EntryApr 8, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
Texas
County
Motley
Region
ERCOT
Developer
Buzios Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 59904 Cottonwood - 23922 White River Ckt 2
Data Source
Live · ERCOT
No news available for this project.