Funston Solar (Alternative POI Lone Star)
351.4 MW generation in Jones, TX · In queue since February 2024 · Proposed COD July 2027
351.4 MW
Capacity
1
Components
Solar
2y 2m
In Queue
IA Executed
IA Status
Signed Oct 2024
Queue → IA
8 months
IA → COD
2y 9m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-01
State
TX
County
Jones
Region
ERCOT
Developer
Funston Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68000 West Shackelford _x0013_ 68004 Phantom Hill Circuit 2
Data Source
LBNL + Live
Linked EIA Plant
Funston Solar
EIA Plant ID: 67359