Queen Mesa Solar II — Project Summary

Queue ID
ERCOT-29INR0013
Capacity
300 MW
Technology
Solar
Status
active
Location
Crane, TX
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
IA Status
Facility Study

Queen Mesa Solar II

ERCOT-29INR0013BetaActiveSolarERCOTLBNL + Live

300 MW generation in Crane, TX · In queue since June 2024 · Proposed COD March 2031

300 MW

Capacity

1

Components

Solar

1y 10m

In Queue

Facility Study

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

6y 9m

Facilities Study50%
Queue EntryJun 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-03-21

Project Details

State

TX

County

Crane

Region

ERCOT

Developer

NextEra Energy Interconnection Holdings, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

76000 North McCamey 345kV

Data Source

LBNL + Live

No news available for this project.