Aurelius 2 Solar
445.4 MW generation in Deaf Smith, TX · In queue since December 2023 · Proposed COD September 2028
445.4 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
State
TX
County
Deaf Smith
Region
ERCOT
Developer
IP Roman II, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD).