Aurelius Wind
ERCOT-29INR0004BetaActiveWindERCOTLBNL + Live
623 MW generation in Deaf Smith, TX · In queue since August 2023 · Proposed COD June 2028
623 MW
Capacity
1
Components
Wind
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntryAug 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Deaf Smith
Region
ERCOT
Developer
IP Roman, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23908 Deaf Smith station 345 kV
Data Source
LBNL + Live
No news available for this project.