Grayback Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
221.81 MW generation in Wilbarger, Texas · In queue since November 2025 · Proposed COD September 2029
221.81 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryNov 5, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-01
Project Details
State
Texas
County
Wilbarger
Region
ERCOT
Developer
Grayback Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
To Riley7A Substation (#6101)
Data Source
Live · ERCOT
No news available for this project.