Dilley Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
200.7 MW generation in Frio, Texas · In queue since December 2025 · Proposed COD June 2028
200.7 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 6m
Pre-Study0%
Queue EntryDec 23, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
Texas
County
Frio
Region
ERCOT
Developer
AETS Development Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLS
Data Source
Live · ERCOT
No news available for this project.