Kilby1 Part 4 Large Block Simple Cycle
BetaActiveGas - Combustion (gas) TurbineERCOTLive · ERCOT
950 MW generation in Reeves, Texas · In queue since November 2025 · Proposed COD April 2028
950 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 5m
Pre-Study0%
Queue EntryNov 18, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-20
Project Details
State
Texas
County
Reeves
Region
ERCOT
Developer
Energy Forge One LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345KV 11098 SLKSW – 60404 SOLSTICE Ckt 1 & Ckt 2
Data Source
Live · ERCOT