Neal Battery
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
120.52 MW storage in Wharton, Texas · In queue since October 2025 · Proposed COD April 2029
120.52 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryOct 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-03
Project Details
State
Texas
County
Wharton
Region
ERCOT
Developer
CH Neal Battery LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap of 138kV 8750 CHARMERP4A - 8127 South Lane City
Data Source
Live · ERCOT
No news available for this project.