Vista Bluff Wind II "Alternate POI"
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
290.4 MW generation in Upton, Texas · In queue since September 2025 · Proposed COD December 2029
290.4 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 3m
Pre-Study0%
Queue EntrySep 22, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
Texas
County
Upton
Region
ERCOT
Developer
Vista Bluff Windpower, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345 kV (76000) North McCamey - (59903) Bearkat (Benedum 345 kV station that LCRA will build part of 24RPG024).
Data Source
Live · ERCOT