Viento Bravo Wind
ERCOT-28INR0434BetaActiveWindWind TurbineERCOTLive · ERCOT
366.51 MW generation in Jim Hogg, TX · In queue since October 2025 · Proposed COD July 2028
366.51 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Signed Dec 2025
Interconnection Timeline
Queue → IA
2 months
IA → COD
2y 7m
Total Duration
2 months
Construction0%
Queue EntryOct 3, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 31, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2028-07-06
Project Details
State
TX
County
Jim Hogg
Region
ERCOT
Developer
Webb Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1
Data Source
Live · ERCOT
No news available for this project.