Maratua Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
100.51 MW generation in Grimes, Texas · In queue since October 2025 · Proposed COD December 2029
100.51 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryOct 3, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
Texas
County
Grimes
Region
ERCOT
Developer
BDPU Solar Maratua, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
New 138kV connection on 9 BEDIAS – 4 IOLA
Data Source
Live · ERCOT
No news available for this project.