Prairie Branch Solar — Project Summary

Queue ID
ERCOT-28INR0422
Capacity
301.14 MW
Technology
Solar
Status
active
Location
Montague, Texas
Region
ERCOT
Developer
Prairie Branch Solar
IA Status

Prairie Branch Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

301.14 MW generation in Montague, Texas · In queue since September 2025 · Proposed COD June 2028

301.14 MW

Capacity

0

Components

6 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

2y 9m

Pre-Study0%
Queue EntrySep 9, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-24

Project Details

State

Texas

County

Montague

Region

ERCOT

Developer

Prairie Branch Solar

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV #1730 Krum West - #6111 Riley Ckt 1

Data Source

Live · ERCOT

No news available for this project.