PRI Solar — Project Summary

Queue ID
ERCOT-28INR0419
Capacity
63.84 MW
Technology
Solar
Status
active
Location
Howard, Texas
Region
ERCOT
Developer
BHER Power Resources, Inc.
IA Status

PRI Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

63.84 MW generation in Howard, Texas · In queue since July 2025 · Proposed COD January 2027

63.84 MW

Capacity

0

Components

8 months

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

1y 6m

Pre-Study0%
Queue EntryJul 29, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-31

Project Details

State

Texas

County

Howard

Region

ERCOT

Developer

BHER Power Resources, Inc.

Utility

Entity

ERCOT

Point of Interconnection

The 345 kV Falcon Seaboard (#1025) substation; Oncor

Data Source

Live · ERCOT

No news available for this project.