Tolivar Power Plant Phase 2
BetaActiveGas - Internal CombustionERCOTLive · ERCOT
224.5 MW generation in Reeves, Texas · In queue since July 2025 · Proposed COD July 2027
224.5 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2 years
Pre-Study0%
Queue EntryJul 29, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-30
Project Details
State
Texas
County
Reeves
Region
ERCOT
Developer
Pecos Power Plant, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 KV 38055 Saltdraw-38043 COWPEN
Data Source
Live · ERCOT
No news available for this project.