Ouroboros Grid BESS 1
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
200.82 MW storage in Cameron, Texas · In queue since July 2025 · Proposed COD June 2028
200.82 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 11m
Pre-Study0%
Queue EntryJul 29, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
Texas
County
Cameron
Region
ERCOT
Developer
Ouroboros Grid BESS Unit 1
Utility
—
Entity
ERCOT
Point of Interconnection
POIB: #88337 Chalybe 345 kV (expansion of the #8735 Chalybe 138 kV – to be connected by double circuit line to #79500 Palmito 345 kV)
Data Source
Live · ERCOT
No news available for this project.