Treehouse Solar — Project Summary

Queue ID
ERCOT-28INR0394
Capacity
281.77 MW
Technology
Solar
Status
active
Location
Grimes, Texas
Region
ERCOT
Developer
Treehouse Solar, LLC
IA Status

Treehouse Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

281.77 MW generation in Grimes, Texas · In queue since July 2025 · Proposed COD November 2028

281.77 MW

Capacity

0

Components

8 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 4m

Pre-Study0%
Queue EntryJul 29, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-13

Project Details

State

Texas

County

Grimes

Region

ERCOT

Developer

Treehouse Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap the 345 kV Jewett (#3390) - Singleton (#44645) line

Data Source

Live · ERCOT