Horsepower BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
257.5 MW storage in Bexar, Texas · In queue since December 2025 · Proposed COD January 2028
257.5 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 1m
Pre-Study0%
Queue EntryDec 17, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-31
Project Details
State
Texas
County
Bexar
Region
ERCOT
Developer
Horsepower BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
POI is 138 kV Howard Substation (Bus# 5230) (SSWG bus name: HOWARD), NMMS station code: S1
Data Source
Live · ERCOT
No news available for this project.