Tri-X BESS 1 SLF
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
205.3 MW storage in Crane, Texas · In queue since August 2025 · Proposed COD December 2027
205.3 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 4m
Pre-Study0%
Queue EntryAug 18, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
Texas
County
Crane
Region
ERCOT
Developer
Crane I Solar Electric, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138 kV Soda Lake (#76026)
Data Source
Live · ERCOT
No news available for this project.