Galaxy Storage 2
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
201.87 MW storage in Ellis, Texas · In queue since June 2025 · Proposed COD October 2029
201.87 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntryJun 19, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-10-30
Project Details
State
Texas
County
Ellis
Region
ERCOT
Developer
Galaxy Solar 2, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navarro Switch (LST) (#68091) BKR 3B3134/3B3127
Data Source
Live · ERCOT
No news available for this project.