Barranca Wind 1 — Project Summary

Queue ID
ERCOT-28INR0375
Capacity
300.9 MW
Technology
Wind
Status
active
Location
Jim Hogg, Texas
Region
ERCOT
Developer
Barranca Wind Energy, LLC
IA Status

Barranca Wind 1

BetaActiveWind - Wind TurbineERCOTLive · ERCOT

300.9 MW generation in Jim Hogg, Texas · In queue since July 2025 · Proposed COD June 2028

300.9 MW

Capacity

0

Components

8 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

2y 11m

Pre-Study0%
Queue EntryJul 29, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

Texas

County

Jim Hogg

Region

ERCOT

Developer

Barranca Wind Energy, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap the 345 kV CENIZO (#80225) - DELSOL (#80307) line

Data Source

Live · ERCOT