Cherry Sage Storage 1 SLF
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
150.28 MW storage in Concho, Texas · In queue since April 2025 · Proposed COD February 2029
150.28 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryApr 25, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-23
Project Details
State
Texas
County
Concho
Region
ERCOT
Developer
Cherry Sage Storage 1 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
(#60423) TREADWELL 138kV.
Data Source
Live · ERCOT
No news available for this project.