Galaxy I Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
99.42 MW generation in Ellis, Texas · In queue since April 2025 · Proposed COD October 2028
99.42 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-30
Project Details
State
Texas
County
Ellis
Region
ERCOT
Developer
Galaxy Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Stainback Switch (bus #2217) - Elrod Switch (bus #3159)
Data Source
Live · ERCOT
No news available for this project.