Cowboy Power Gas Plant
BetaActiveGas - Internal CombustionERCOTLive · ERCOT
251.53 MW generation in San Patricio, Texas · In queue since August 2025 · Proposed COD October 2028
251.53 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 2m
Pre-Study0%
Queue EntryAug 18, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-16
Project Details
State
Texas
County
San Patricio
Region
ERCOT
Developer
Vaquero Power, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 8249 Angstrom - 8624 Grissom
Data Source
Live · ERCOT