Ringtail Energy Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
203.8 MW storage in Archer, Texas · In queue since April 2025 · Proposed COD December 2028
203.8 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryApr 25, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-15
Project Details
State
Texas
County
Archer
Region
ERCOT
Developer
PowerPulse LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Bus # 1446, Lake Wichita, 138 kV
Data Source
Live · ERCOT
No news available for this project.