Maximino Road BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
206 MW storage in Comal, Texas · In queue since March 2025 · Proposed COD May 2028
206 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 2m
Pre-Study0%
Queue EntryMar 24, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-31
Project Details
State
Texas
County
Comal
Region
ERCOT
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7170 BERGHEIM 138kV
Data Source
Live · ERCOT
No news available for this project.