Bastion BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
154.3 MW storage in Matagorda, Texas · In queue since July 2025 · Proposed COD November 2028
154.3 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 4m
Pre-Study0%
Queue EntryJul 7, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
Texas
County
Matagorda
Region
ERCOT
Developer
BESS BASTION LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Blessing Substation 138 kV (ID 8121)
Data Source
Live · ERCOT
No news available for this project.