Corralitos Wind 4
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
195.4 MW generation in Zapata, Texas · In queue since June 2025 · Proposed COD May 2028
195.4 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 11m
Pre-Study0%
Queue EntryJun 13, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-31
Project Details
State
Texas
County
Zapata
Region
ERCOT
Developer
Las Crestas Wind Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C - 80307 DELSOL7C)
Data Source
Live · ERCOT
No news available for this project.