Cielo Vista Power Gas Plant
BetaActiveGas - Internal CombustionERCOTLive · ERCOT
334.7 MW generation in Duval, Texas · In queue since August 2025 · Proposed COD June 2028
334.7 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 10m
Pre-Study0%
Queue EntryAug 18, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
Texas
County
Duval
Region
ERCOT
Developer
Cielo Vista Power, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1
Data Source
Live · ERCOT
No news available for this project.