Barkley Creek Solar — Project Summary

Queue ID
ERCOT-28INR0324
Capacity
312.37 MW
Technology
Solar
Status
active
Location
Lampasas, Texas
Region
ERCOT
Developer
174 Power Global Properties, LLC
IA Status

Barkley Creek Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

312.37 MW generation in Lampasas, Texas · In queue since August 2025 · Proposed COD October 2029

312.37 MW

Capacity

0

Components

7 months

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 2m

Pre-Study0%
Queue EntryAug 26, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-15

Project Details

State

Texas

County

Lampasas

Region

ERCOT

Developer

174 Power Global Properties, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch (Bus# 3422)

Data Source

Live · ERCOT

No news available for this project.