Barkley Creek Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
312.37 MW generation in Lampasas, Texas · In queue since August 2025 · Proposed COD October 2029
312.37 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryAug 26, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-10-15
Project Details
State
Texas
County
Lampasas
Region
ERCOT
Developer
174 Power Global Properties, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch (Bus# 3422)
Data Source
Live · ERCOT