Velociraptor BESS II
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
261.29 MW storage in Ector, Texas · In queue since May 2025 · Proposed COD November 2028
261.29 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryMay 27, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-17
Project Details
State
Texas
County
Ector
Region
ERCOT
Developer
Greyhound BESS 3 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
#11028 Odessa EHV SW - #11010 Wolf Switch 345K
Data Source
Live · ERCOT
No news available for this project.